L&T commissions state-of-the-art project to NWPGCL

L&T’s scope of work included design, engineering, supply, installation and commissioning of the complete power plant on a back-to-back turnkey basis for Marubeni Corporation of Japan, with Gas Turbines, Steam Turbine and Generators from Mitsubishi Hitachi Power Systems, Japan.

Larsen & Toubro Limited (L&T) has successfully commissioned and handed over the state-of-the-art 360 MW Bheramara Combined Cycle Power Plant Development Project to North West Power Generation Company Limited (NWPGCL), a fully owned subsidiary of Bangladesh Power Development Board (BPDB), on January 5, 2018. After performance testing, the plant capacity has been declared as 410 MW by the customer. This power plant is based in Bheramara of Kushtia District in the western sector of Bangladesh, which is approximately 250 km from Kolkata, India.

L&T’s scope of work included design, engineering, supply, installation and commissioning of the complete power plant on a back-to-back turnkey basis for Marubeni Corporation of Japan, with Gas Turbines, Steam Turbine and Generators from Mitsubishi Hitachi Power Systems, Japan. Work on this Japan International Cooperation Agency (JICA)-funded project had started in July 2014 and the power plant was partly commissioned earlier in Open Cycle, which was handed over to NWPGCL for commercial operation in May 2017.

Shailendra Roy, CEO & Managing Director, L&T Power & Whole-Time Director, L&T, said, “The fact that two power plants were commissioned in quick succession in Bangladesh, one in December 2017 and the other in January 2018, speaks volumes about L&T’s scale of operations. We thank the Bangladesh authorities for reposing faith in our capabilities.”

Leave a Reply