Juniper Green Energy Limited has successfully commissioned around ~64 MWp of new renewable energy capacity across two key projects in Gujarat and Maharashtra. This milestone, which includes the commissioning of a wind power project and the solar component of its hybrid power project in these respective states, highlights the company’s effective execution capabilities and continued commitment to driving India’s clean energy transition.
Juniper Green Energy commissioned ~28 MW of wind power capacity from its 70 MW wind power project in Devbhumi Dwarka, Gujarat, through its subsidiary Juniper Green Kite Private Limited. This capacity was commissioned on October 15, 2025, approximately 4 months ahead of its Scheduled Commercial Operation Date (SCOD) of February 7, 2026. Juniper Green Kite Private Limited executed a Power Purchase Agreement with Gujarat Urja Vikas Nigam Limited for the total 70 MW wind power project, on February 8, 2024.
The company also commissioned the ~36 MWp capacity solar component of its 133 MWp hybrid power project in District Nanded, Maharashtra, through its subsidiary Juniper Green Spark Ten Private Limited. This plant, commissioned on October 12, 2025, was commissioned 13 months ahead of schedule. Juniper Green Spark Ten Private Limited executed a Power Purchase Agreement with Maharashtra State Electricity Distribution Company Limited on November 18, 2024.